Advertisement

New World carried on selling flats at The Pavilia Farm III after concrete defects were found, as engineers didn’t deem them serious

  • The developer enjoyed two lively sales weekends after the defects were found in two blocks later earmarked for demolition
  • Some buyers struck a forgiving tone, saying New World had acted properly and would learn from the experience

Reading Time:2 minutes
Why you can trust SCMP
3
New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse
New World Development kept selling flats at The Pavilia Farm III – including two tower blocks earmarked this week for demolition – on June 20 and 27, days after defects were found, because engineers did not consider them serious enough to warrant drastic action.
Advertisement

The sale on June 20 was a success, with the developer selling 169 of the 173 flats on offer for a total haul of about HK$2.7 billion (US$347.57 million) in one day. The biggest customer forked out HK$54 million for three flats, while a unit at Tower 1A sold at HK$29,037 per square foot, a price record for Phase III.

A week later New World ratcheted up another bumper weekend, selling 79 of 85 flats at The Pavilia Farm III, in Tai Wai, even after a 24 per cent price increase from a month earlier.

“As the test result was preliminary, maybe the [developer] wanted to double confirm” before taking drastic action, said CGS-CIMB Securities’ managing director Raymond Cheng, adding that the sales outcome would not have been affected by much even if the test results had been known. “Of course it’s not ideal and very good, but it’s not intentional.”

YouTube video player

Days later, on July 3, New World’s contractor reported that the concrete strength in sections of the wall base in two of the seven tower blocks in the project’s latest phase failed to meet design standards. It was another five days before the developer took the unprecedented step of announcing its plan to tear down and rebuild the affected towers, and compensate customers for delaying their delivery by nine months.

Advertisement
Advertisement